Galan on track for Argentine lithium brine production

06/12/2023 - 13:16

Bookmark

Save articles for future reference.

Galan Lithium is on schedule for initial production at its Hombre Muerto West lithium project in Argentina by the first half of 2025, with construction of its first evaporation pond now 65 per cent complete. Pond liners have arrived on-site and installation is set to begin this month, ahead of filling the pools in next year’s first quarter.